Work: Sub Base, Base and Hard Shoulder
Event Unit Detail ID
Burrow Materials
Providing and laying Median and Island above road level with approved Material deposited including compacted as per Drawing and
Specifications. ( using material from borrow area)
73
Cement Treated Subbase
Providing, laying and spreading Material on a prepared sub grade, adding the designed quantity of cement to the spread Material, mixing in place , grading and compacting at OMC to achieve the desired unconfined compressive strength and to form a layer of sub-base/base as per Drawing and Technical Specifications.
66
Cement Treated Subbase, Pulverizing
Providing, laying and spreading soil on a prepared sub grade, pulverizing, adding the designed quantity of cement to the spread soil, mixing in place , grading and compacting at OMC to achieve the desired unconfined compressive strength and to form a layer of sub-base/base as per Drawing and Technical Specifications.
65
Crusher Run Macadam
Crusher Run Macadam Base and sub-baseProviding and laying Crusher Run Macadam on a prepared surface, spreading and mixing , watering and compacting to form a layer of sub-base/Base course as per Drawing and Technical Specifications.
70
Dry Bound Macadam, Grading-I
Providing, laying, spreading and compacting stone aggregates of specific sizes to dry bound macadam including spreading in uniform thickness, hand packing, rolling and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, and compacting to the required density as per Drawing and Technical Specifications. Grading-I
76
Dry Bound Macadam, Grading-II
Providing, laying, spreading and compacting stone aggregates of specific sizes to dry bound macadam including spreading in uniform thickness, hand packing, rolling and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, and compacting to the required density as per Drawing and Technical Specifications. Grading-II
77
Footpath Seperator
Providing and making footpath/separator of 150 mm compacted granular sub base and 25 mm thick cement concrete grade M 15, over laid with pre cast concrete tiles in cement mortar 1:3 including provision of all drainage arrangements but excluding Kerb channel as per Drawing and Technical Specifications.
74
Furrows
Making 50 mm x 50 mm furrows, 50 mm deep, 450 to the center line of the road and at one meter interval in the existing thin bituminous wearing coarse including sweeping and disposal of excavated Material .
67
Granular Sub Base, Manual Means
Providing and laying granular sub-base on prepared surface, mixing at OMC, and compacting to achieve the desired density, complete as per Drawing and Technical Specifications. Manual Means
64
Granular Sub Base, Mechanical Means
Providing and laying granular sub-base on prepared surface, mixing at OMC, and compacting to achieve the desired density, complete as per Drawing and Technical Specifications. Mechanical Means
63
Inverted Choke
Providing, laying, spreading and compacting screening / coarse sand of specified grade in uniform layer on a prepared surface and compacting to form a inverted Choke as per Drawing and Technical Specifications.
68
Roadway Cutting Material
Providing and laying Median and Island above road level with approved Material deposited including compacted as per Drawing and Specifications. ( using material from Roadway excavation).
72
Telford Base Block Pitching
Providing laying, spreading watering, levelling and compaction of Telford base ( Block pitching) as per Drawing and Technical Specifications.
75
Water Bound Macadam, Manual Means
Providing, laying, spreading and compacting Water bound macadam including brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density as per Drawing and Technical Specifications. Manual Means
69
Water Bound Macadam, Mechanical Means
Providing, laying, spreading and compacting Water bound macadam including brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density as per Drawing and Technical Specifications.
71
Wet Mix Macadam, Base Course, B1 Material
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC laying in uniform layers in sub base / base course on well prepared surface and compacting to achieve required density as per Drawing and Technical Specifications. A Base course with B1 material
78
Wet Mix Macadam, Base Course, B2 Material
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC laying in uniform layers in sub base / base course on well prepared surface and compacting to achieve required density as per Drawing and Technical Specifications. A Base course with B2 material
79
Wet Mix Macadam, Sub Base Course, S1 Material
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC laying in uniform layers in sub base / base course on well prepared surface and compacting to achieve required density as per Drawing and Technical Specifications. A Sub Base course with S1 material
80
Wet Mix Macadam, Sub Base Course, S2 Material
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC laying in uniform layers in sub base / base course on well prepared surface and compacting to achieve required density as per Drawing and Technical Specifications. A Sub Base course with S2 material
81